INSTALLATION MANUAL
|
STEP 7: PAGE 1 OF 2
|
SIDEWALL INSTALLATION USING TRAPEZOIDS: MATERIAL NEEDED
The Left Sidewall Modules solid kickplates should be
trimmed to fit slope of foundation as the front wall was see Diagram 3.2 & 3.3 of step
3.
DIAGRAM 5.0
Once the trimming has been completed Start placing the correct numbered
Module in the Side Bottom Track at the front wall. Because the exact pitch of the roof is
not known,the vertical mullions of the Modules will run past the outside of the Rafter.
After all Modules are in and together, Level and plumb your walls,but do not secure. When
this has been completed you are ready to mark and cut the vertical mullions to fit under
the Rafter. This height is found by drawing a line on the mullions at the bottom of the
Rafter. Draw a line 1/16" down from the original mark.(this allows for the thickness
of the Sidewall Bracket) Also Mark Rafter at each side of vertical mullions.This will be
the location of the Sidewall Bracket. |
DIAGRAM 5.0
|
|